H.L. PASSEY ENGINEERING PVT LTD Bhopal : Water Works, Construction Civil Engineer

+ Ask Question / Post resume
Results 1 to 3 of 3
  1. Post Count Number #1
    Super Moderator
    Join Date
    April 18th, 2008
    Location
    Tuticorin
    Posts
    7,026

    H.L. PASSEY ENGINEERING PVT LTD Bhopal : Water Works, Construction Civil Engineer

    H.L. PASSEY ENGINEERING PVT. LTD. Around Bhopal : Project Manager

    Keywords: Water Works; Civil Engineer; Construction; Water Supply

    Designation: Project Manager
    Experience: 7 - 12 Years
    Location: Around Bhopal
    Compensation:
    Rupees 2,50,000 - 7,50,000
    plus perks
    Education:
    UG - B.Tech/B.E. - Civil, Environmental,Diploma - Civil
    PG - M.Tech - Civil, Environmental
    Industry Type: Construction/ Engineering/Cement/Metals
    Functional Area: Site Engg., Project Management
    Posted Date: 25 Feb

    Job Description:
    To be able to co-ordinate between the clients and the consultants for smooth execution of work;
    to be able to get work executed on site;
    to monitor billing and payments for the works being handled

    Desired Candidate Profile:
    Should have managerial skills. Minimum Experience 7 years

    Company Profile:
    The company is 54 years old managed by professional in various fields of engineering

    Executive Name: Mr. Prabodh Passey

    Address:
    HL PASSEY ENGINEERING PVT LTD
    72 /A, Industrial Area
    Govindpura
    Bhopal,M.P,INDIA 462023

    Email Address: prabodhpassey@yahoo.com

    Telephone: Not Mentioned

    Keywords: Water Works; Civil Engineer; Construction; Water Supply

  2. Post Count Number #2
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    Re: H.L. PASSEY ENGINEERING Bhopal : Water Works, Construction Civil Engineer

    To,
    Sub.:- Application for the post of Sr. Engineer ( Billing ) .
    Sir,
    I offer my candidature for the said post in reference to your advertisement in daily News Paper.
    My detailed curriculam - vitae is enclosed herewith for your kind consideration.
    I am confident that I possess the required qualication and experience , A hope you will give me a chance to prove my worthiness for the post applied for and serve in your esteemed organization.
    Assuring you of my best and qualitative services at all time.

    Thanking you ,

    Your faithfully
    Date :-

    Balkrishna Mishra

    C U R R I C U L A M VI T A E
    1. PROPOSED POSITION - CIVIL ENGINEER
    2. NAME - BALKRISHNA MISHRA
    3. DATE OF BIRTH ( AGE ) - 3rd December 1967
    4. NATIONALITY - Indian
    5. ADDRESS - 127, Vaishnav Building., Surendra Place
    Hoshangabad Road, Bhopal
    6. CONTACT - Mob. 09981906451
    Email : mishra_bhopal AT rediffmail.com
    7. ACEDEMIC - B.Sc.(1st year) from Sagar University QUALIFICATION in year 1988
    8. TECHNICAL - 1. DIPLOMA in
    QUALIFICATION CIVIL ENGINEERING( 1st Div.)
    from Govt. S.V. Polytechnic Bhopal in year 1993 ( part time course)

    CERTIFICATE OF ‘DRAUGHTSMAN CIVIL’( 1st Div.)
    From M.I.T.I. Bhopal in 1987.

    9. WORKING EXPERIENCE E - 21 YEARS ( from 1987 to Date)
    10. LANGUAGE KNOWN - Language English Hindi
    Speaking Good Excellent
    Reading Excellent Excellent
    Writing Excellent Excellent
    11. COMPUTER EXPOSURE - MS EXCEL MS WORD AUTOCAD
    EXCELLENT EXCELLENT EXCELLENT

    12. EMPLOYMENT RECORD :-
    a. FROM - Jan.2009 To Till date
    EMPLOYER - SCC Projects Pvt. Ltd , Bhopal
    POSITION HELD - Billing Engineer
    DESCRIPTION OF - Contractor & Client Billing
    DUTIES

    b. FROM - Feb.2008 To Jan.2009
    EMPLOYER - Ramky Infrastructure Limited T.T.Nagar, Bhopal ( MP )
    POSITION HELD - Senior Engineer (Billing )
    DESCRIPTION OF - Contractor & Client Billing
    DUTIES Coordination to Store & QC deptt.

    c. FROM - Aug 2006 To Feb.2008
    EMPLOYER - Shukla Constructions Co. Pvt. Ltd Bittan Market, Bhopal ( MP )
    POSITION HELD - Manager (Technical )
    DESCRIPTION OF - Liaison to concern department, Estimation
    DUTIES - Site Coordination, Bill Checking

    d. FROM - May 2002 To Aug 2006
    EMPLOYER - ADS Consultants
    E – 5 / 70 , Arera Colony Bhopal
    POSITION HELD - Junior Engineer
    DESCRIPTION OF - Estimation of Bridges, Aqueducts, Buildings,
    DUTIES Supervision, BOQ & Valuation of Buildings

    e. FROM - Nov . 1989 To April 2002
    EMPLOYER - C.V. KAND Consultants
    E – 2 / 136 , Arera Colony Bhopal
    POSITION HELD - Draughtsman / Junior Engineer
    DESCRIPTION OF - Detailed drawing, Estimation of Bridges,
    DUTIES Aqueduct and, Supervision of
    Buildings & Colony.


    f. FROM - Aug . 1987 To Nov . 1989
    EMPLOYER - Center for Architectural Design, Bhopal
    POSITION HELD - Draughtsman

    Balkrishna Mishra

  3. Post Count Number #3
    On probation
    Join Date
    May 26th, 2011
    Location
    Pakistan,Lahore
    Posts
    1

    Civil Engineer InfraStructure works

    1.DESCON Engineering Limitd (July 2005 to Oct 2009 )

    Client: National Highway Authority

    Worked as Manager for Construction of Islamabad Peshawar Motorway. Project (M-I). Key responsibilities are to check quality of all construction activities of Road works as well as structural and ancillary works. Task performed are listed as follows.

    (i) Roads Works

    Earthworks, Sub Base, Aggregate Base Course. Asphalt Base Course, Prime Coat, Asphalt Wearing Course and Tack Coat.
    Drainage Plans of the Motorway at X-Slopes, Super Elevations, Diversion of Existing Water Channels, Existing Roads.
    Erosion Works for Protection of Slopes and Toe of the Motorway.

    (ii) Structure works
    Major Structure: -

    River Kabul Bridge
    2.0M Dia. piling worker with Reverse Rotary system. Using Bentonite slurry for the protection of the borehole.
    Casting of Pre-Stressed I-Girders 45.0 M Long, approval of Bar Bending Schedules as Per ASTM Standards, Cable Profile making as per drawings and Stronghold, Germany Standards.
    Pre-stressing of Post-Tensioning Methods of Girders.
    Pre-Stressing results for both/one end Stressing and ensuring Permissible limits of elongation and elastic recovery.
    Computation of Jacking force and its applications to the Pre-stress wires including losses due to friction.
    Grouting of conduits for Pre-Stress cable. Ensuring permissible pressure to the Grout. Use of expansive additives (Flow Cable of Master Build).
    Casting of Transoms, Bearing seats and other Structural parts of the Bridge.
    Launching of Pre-Stress girders including placing of Electrometric Bearing Pads.
    Casting of Pre-Stress Diaphragms and Deck slab.
    Fixing of Expansion Joints for Bridge Deck slab.
    Similar activities checking on other small four bridges 25.0 m span length each.

    (iii) Minor Structures:
    Exact location of Box Culverts /Pipe Culverts, Underpasses, and cattle creeps, including excavation, performing F.D.T Preparation of Bar Bending Schedules as Per Drawings, fixing of formwork and Concreting in Parts Bed Walls, Roof, Wing Walls, apron.

    (vi) Preparation of Geotechnical investigation of Exploratory Bore holes for Bridges & loads Tests.


    2.Ayaz Builder Xin-Jiang Bexin (2 Feb, 2005 to July 2005)

    Client:National Highway Authority

    Gwadar- Turbat- Ratodero Motorway Project worked as structure Engineer for construction of (11) Bridges over water streams and 350 Culverts of flood water and on water Channels.
    Duties of Work at the projects as follows:
    Preparation of Shop drawings for all structures Bridges and Culverts.
    Selection of Location of Culverts as per site conditions and Bridge Abutment location as per topography of the area.

    Supervising Execution of Work as Bridge Engineer Comprising a Team of site Engineers, Supervisor and surveyors.
    Material testing regarding structure works.
    Conducting Geotechnical Investigations and preparation of Design reports of Piles.
    Pile Load Test as per Design.

    3.Al -Khan Construction Compnay (Pvt) Ltd.
    (September 2003 to Nov 2004)
    Client: Natinaol Highway Authority
    Worked as Structure Engineer for 3 Bridges.
    Bridge # 1 250 M Long 16 M Span Lengths
    Bridge # 2 25 M Long
    Bridge # 3 350 M Long 20 M Span Lengths
    Worked as a Team leader of execution of all Bridges.
    Preparation of Shop Drawings.
    Arrangement of Materials.
    Concrete, Cement, Aggregates, Steel Shuttering, Hiring of Man Power.
    Preparation of Construction planes as per Primavera and monitoring the same as per target dates.
    Pile Load Test as per Design.







    4.Descon Engineering Ltd. (October 2002 to September 2003)

    Worked as Cost Control Engineer for Sat Para Dam Project. BHP Zamzama Gas Field Dadu Pakistan.

    Client: Wapda

    Major Tasks

    Budget Preparation of the Project as Per Proposed tender Submitted.
    Implementation of Budget as Per site.
    Procurement of Materials, Subcontractors and Manufacturers
    Preparation of Monthly financial review, Analytical Study and preparing a report for the Profit/Loss for the higher management.
    Resource Management adhering to Project Plan submitted.

    (5) Husnain Construction Company (Pvt) Ltd.
    (August 1997 to October, 2002)
    (Presently name as Husnain Cotex)

    Client: National Highway Authority
    Pindi Bhatian Faisalabad Motorway Project (M-3)
    Joined the firm for tender preparation of the above said project and performed following tasks.

    Prepare the tender of the project along with expert team of engineers for Motorway Construction. Calculation of equipment hrs, Man hrs and cost evaluation of the Project.
    Progress monitoring of four ongoing Road projects of cost 6 Billion Pak Rs.( 300 Million US $)
    Preparing Time extension claims.
    Preparing Tender documents for road projects.
    Preparing claims on delayed payment, escalations, and extra works under FIDIC clauses of contract.
    Preparing claims of unspecified materials other than appendix “C” of the contract documents.
    Miscellaneous construction Assignments. (Construction of farm Houses, Building).
    NFC Employees Housing Society Lahore (Remaining Works)
    EME Employees Housing Society (Remaining Works)

    (6) A.A. Associates (December 1993 to May 1997)

    Bridge Project over River Chenab:

    Client: National Highway Authority
    Worked as Site Inspector

    Project comprises of three Bridges and 2.0 KM of approaches of Bridges Road works.
    Two Prestress Bridges 240M & 280M Long on River Channels east side and west side of River Chenab, and one Railway Bridge of 580 M Long. River Bridges consists of 2.0M Dia Piling with Reverse rotary system and BSP Tera Drill Machine.
    Main Activities at site were as follows:
    Supervision of all construction activities of piles like Boring steel and concreting.
    Supervision of 40.0M long Pre stress girders.
    Supervision of Construction of all other activities like transom construction, lunching, diaphragm construction and Deck slab construction.
    Railway Bridge consists of Raft Foundation and Pile foundations 1.0M Dia. Piling. Pre stress Girders of 25M Long.
    Supervision of stressing, grouting of Pre stress girders.
    Supervision of placement & quality checking of bearing pads & expansion joints as per AASHTO.
    Supervision of construction activities of Approaches like earth work, sub base, aggregate base, and Asphalt courses.

    Telecom Foundation (May 1992 to December 1993)
    Client: PTCL
    Supervision of Construction of OSP works of Telecom Manhole construction.
    Laying of PVC conduits.
    Laying of PTCL Cables.
    Procurement of Materials and subcontractors.
    Inspection from Siemens, Pakistan of Germany.

    Special Experience of Box Girder Bridge Construction.
    Client: National Highway Authority
    Completed one Box Girder Bridge Deck of 40M long, at Manghopir Interchange Layari Expressway Project, Karachi.
    Completed Pre stress / Grouting of Gulbai Box Girder Bridge 55M Long at Karachi Northern Bypass, Karachi.