www.jeltron.com Systems India Pvt Ltd coimbatore : TECHNICAL MARKETING & SERVICE ENGINEERS

+ Ask Question / Post resume
Results 1 to 2 of 2
  1. Post Count Number #1
    Site Admin
    Join Date
    April 17th, 2008
    Location
    Europe
    Posts
    11,588

    www.jeltron.com Systems India Pvt Ltd coimbatore : TECHNICAL MARKETING & SERVICE ENGINEERS

    JELTRON SYSTEMS INDIA PVT LTD INDIA : TECHNICAL MARKETING & SERVICE ENGINEERS
    Company Name : JELTRON SYSTEMS INDIA PVT LTD
    Company Location : INDIA
    Designation (of vacancy) : TECHNICAL MARKETING & SERVICE ENGINEERS
    Company E-mail ID : sathyanarayanan@jeltron.com
    Company Website : http://jeltron.com/

    Job Description, Candidate Profile, Company Profile, Company Address :
    Diploma/Degree- in Electrical & Power electronics with minimum of 1 to 3 years experience. Experience in VFD,PLC & Automation is preferred . But not a must.
    Vacany at Coimbatore, Madurai/ Trichy & Kochi / Trivandrum .
    Jeltron Systems India Pvt Ltd
    11/47, Murugan colony , TVS Nagar, VElandipalayam PO , Coimbatore-641025
    Ph/Fax: 0422-2406445
    coimbatore@jeltron.com
    Last edited by muthukalee; October 28th, 2011 at 12:15 PM.

  2. Post Count Number #2
    IJT addict Guest-IJT's Avatar
    Join Date
    October 15th, 2010
    Location
    Looking for Job
    Posts
    20,894

    EMAIL :
    sravanthi2110 AT gmail.com
    EXPERIENCE SUMMARY
    - Selected through Campus Interview & Successfully Completed 1 Year Training as a GET in IL&FS Engineering Services & had an intensive class room training for 2 months called Bridge -- College to Corporate Training Given by NICMAR 2 year’s 4 Months Experience as Planning Engineer & Project Co-ordinator for 220 KV Transmission Lines.
    - Supply, Erection, Testing & Comissioning of all equipment and materials for 220KV DC/SC line from 400KV Chittoor SS to Palamaneru SS (60KM) with APTRANSCO as client.
    EDUCATION DETAILS
    - B. Tech from JNTU With 79.5%
    COMPUTER SKILLS
    Operating Systems : Windows NT/2000,XP
    Languages : C
    Packages : Ms-office , ERP
    COURSE PROJECT
    - “QUASI RESONANT DC-DC CONVERTED FOR FUEL CELLS WITH ENHANCED EFFICIENCY”.
    PROFESSIONAL EXPERIENCE
    MAYTAS INFRA LIMITED 15th JAN, 2009 to 19th JAN, 2011
    Position : PLANNING ENGINEER,
    Project : 220KV DC/SC line from 400KV Chitoor SS to Palamaneru SS (60KM).
    Clients : AP TRANSCO
    Project Profile : Construction, Supply, Erection, Testing and Commissioning of 220 KV DC/SC line from 400KV Chittoor SS to Palamaneru SS. (60KM)

    Responsibility :
    - Responsible for day-to-day Site Planning and execution with respect of Schedule of Project and quality plan.
    - Study of Tender Documents, Specifications, Terms & Conditions.
    - Preparation of DPR, Plan for the balance work.
    - Over all CLIENT BILLING & SUBCON BILLING.
    - Monitoring of Sub Contractors work execution and Man Power.
    - Calculation of actual quantities and cost savings.
    - Forecasting of Variation of Quantities in actual for client billing.
    - Material Reconciliation Subcontractor wise and comparison with stock at site.
    - Support to the stores department while doing material issue statements and following up with the materials.
    - Creating L2 & L3 network plan for the efficient work of the project.

    MAYTAS INFRA LIMITED 20th JAN, 2011 to Till Now
    Position : PROJECT CO ORDINATOR at Head Office,
    Project : 220KV DC/SC line from 400KV Chitoor SS to Palamaneru SS (60KM).
    Clients : AP TRANSCO
    Project Profile : Construction, Supply, Erection, Testing and Commissioning of 220 KV DC/SC line from 400KV Chittoor SS to Palamaneru SS. (60KM)

    Responsibility :
    - As a project co ordinator Planning, Monitoring & Controlling for the project.
    - Good exposure to Supply Chain Management.
    - Responsible for day-to-day Site Planning and execution with respect of Schedule of Project and quality plan.
    - Co ordination between client and site office.
    - Overall CLIENT BILLING & SUBCON BILLING.
    - Monitoring of Sub Contractors work execution and Man Power.
    - Forecasting of Variation of Quantities in actual for client billing.
    - Entering SUBCON Bills, Work orders of subcontractors and Creation of indent for supply of material in ERP.
    - Preparation of Bill of Quantities as per the Specifications.
    - Co ordination with the team members of the project to make the brief plan regarding execution.
    - Creating shortfall analysis report on daily and weekly basis to calculate the percentage of work executed and improving it in the case of deficit.
    - Raising inspection calls to the client and following it up so as to procure materials effectively.
    - Material Reconciliation Subcontractor wise and comparison with stock at site.
    - Qty estimation according to the drawings for the work and following up with the materials.


    BEHAVIOURAL TRAITS :
    - Won a Silver medal for being topper of school in SSC.
    - Punctual in nature with Good interpersonal skills.
    - Quick Learner and always inquisitive in learning.
    - Ability to work individually and in groups as well.
    - Ability to understand and convince people.