September 3rd, 2010, 02:17 PM
Post Count Number #1
www.gmrgroup.in GMR Group Bangalore,Delhi : Project Management
1.Position : Head - Project Management
Job Code : P- PM001
Role : Analyze the Market and Identify suitable Consultants/Sub consultants Service Providers for Project Implementation. Develop Project Specifications and Bid Documents, manage statutory issues. Maintain high standards in Project Management; provide high quality of workman ship and complete the project on time and handover.
Profile : Graduate or post graduate in Civil Engineering, preferably with an M.B.A Degree with minimum 20 years of experience in Construction; hotel construction, Project management. Must have the experience into successful planning, execution & development of projects.
Location : Delhi and Hyderabad
2.Position : Head - Project Management
Job Code : R - PM001
Role : Lead, manage and direct a number of large highway projects including bridge structures together with a team from project commencement stage till the transition to the asset management group. Effectively liaise with client organizations, design consultants, contractors, suppliers and the community. Should be able to manage contractors with regard to work progress, contract administration and other implementation aspects. Project Agreement administration such as land acquisition, land lease and utility shifting issues, forestland clearances, ROB clearances etc. Responsible for the overall implementation of projects within the time and cost budget.
Profile : Engineer with a strong technical background with a successful track record (min 20 years) in the management and delivery of major highway infrastructure projects.
Location : Bangalore
If you meet any of the above requirements and wish to be a part of a dynamic team, you may forward your detailed resume to jobs@gmrgroup.in with the Position and the Job Code as the Subject matter of the email.
About us :
GMR Group is one of the fastest growing infrastructure organisations in the country with interests in Airports, Energy, Highways and Urban Infrastructure (including SEZ). Employing the Public Private Partnership model, the Group has successfully implemented several infrastructure projects in India.
Contact us :
GMR Group,
IBC Knowledge Park, Phase 2, "D" Block,
9th Floor, 4/1, Bannerghatta Road,
Bangalore - 560 029,
Karnataka,
India
T : +91 80 40432000
F : +91 80 40432180
http://www.gmrgroup.in
-
May 6th, 2011, 01:28 PM
Post Count Number #2
IJT addict
R.PRABHAKARAN
Cell No— 9962111139.
E mail – rprabha1969@yahoo.com
Synopsis :
I would like to create a niche for myself in the organization and the industry. I wish to use my techno–managerial skills to bring about dynamic results at my work place, which would lead to substantial & rewarding outputs, and setting up my organization as the benchmark of best trade practices in the industry .
Work History
First Employer : Sanco Contrans Limited.
Designation : Site Supervisor -- From Dec 1989 to Dec 1990 :
Responsibilities;-
- Industrial - Building completed about 15,000 sq m.
- Supervising all civil & structural related activities.
- Progress & monitoring as per schedule.
Second Employer : Vandana Housing Corporation
Designation : Site Supervisor -- From July 1990 to Jan 1992 :
Responsibilities;-
- Multi- Storied Building completed about 15,000 sq m/ Each Building.
- Marking work for all civil & structural related activities.
- M - Book preparing for Vendor payments.
Third Employer : Rajyog Construction Limited
Designation ; Site Supervisor -- From Dec 1992 to Oct 1998
Responsibilities;-
- 30 M depth 600 dia pile, pile cap, with floating R. c. Columns
- 2 no’s of Multi- Storied Building completed about 30,000 sq m each
- Planning , Billing of all civil activities , Progress & monitoring as per schedule.
Fourth Employer ; Bay City Developers (p) Ltd.
Designation : Site Engineer -- From Mar 2000 to Jan 2002
Responsibilities;-
- Project Controlling & Schedule Monitoring, Monitoring Planned Vs Achieved Progress.
- Co-ordinate Activities, Client Co-ordination, Management Reporting.
- Analyzing & Presenting Weekly & Monthly Progress Review
- Preparation of Documents, Detailed Execution Plans & Work Methods of construction.
- Technical follow-up Design Drawings / Specifications, Approvals.
Fifth Employer : Mangala Engineering Construction Company
Designation : Senior Engineer -- From May 2002 to Jul 2005 :
Responsibilities ;-
- All in Raft foundation with R C. Columns framed Structures
- Land procurement for Residential Building Construction purposes.
- About 8 no’s of Flats completed each 2000 sq m.
- Attending project meetings & Certifying contractor bills.
- Interacting with Clients, Architect, structural designer as well as vendors.
- Full fill the statutory requirements.
Sixth Employer : C B Richard Ellise Pvt Ltd (Australian Company.)
Designation : Asst, Manager Projects -- From Sep 2006 to Oct 2007
Achievements ;-
- Area about 18, 00,000 lakhs sft of “OLYMPIA TECH IT PARK “@ Guindy.
- To lead projects in one or more of the departments work areas.
- To develop particular work areas & avoid the financial loss, law suits & down time.
- A day-to-day technical work on consultancy and research projects including timely completion o f milestone deliverables to cost and quality.
- Provide technical advice and guidance to existing members and other clients.
- Organizing and lead project meetings.
- Assist with marketing of the departments services to industry Continue to enhance technical and managerial skills by having an awareness of
- New concrete mixing chemical products and participating in staff training to assist in personal development.
- Planning & scheduling for Sewage Treatment Plant(anaerobic digester plant ) Water treatment Plant ,Under Ground Sumps (2.KLD lit capacity / Each ),
Previous Employer : Jones Lang LaSalle Maghraj. (Projects & Developments)
Designation ; Asst, Manager Civil -- From Nov 2007 to Oct 2008
Achievements ;-
- Planning and progress monitoring in line with project schedule.
- Soil investigation and area grading works.
- Preparing quality action plan and quality assurance plan for civil and structural works
in Accordance with latest standards.
- Supervising all civil and structural related activities of the project such as strip
Foundation .
- Power house and DG house building, chiller plant, switchyard and switchyard control
Room water treatment plant, storage and service tank structures, roads and
drainage works.
- Preparing procurement schedule (Bill of quantities) for the client.
- Preparing & checking bar bending schedule for all foundation.
- Supervised the fire fighting works of the plant which involves holiday test and wrapping
Coating works.
- Prepared reconciliation statement for the client & certifying the contractor bills.
- Area 18,000 Sq.M PE B structures for Nokia Ph—3 Expansion.
- This project is controlled by Finland Engineers Team.
Personal Profile
Father’s Name Mr. R.RAJARAM
Date of Birth 5th May 1969
Education Higher Secondary Level
Qualification Diploma in Civil Engg (Finished - 1989)
Linguistic ability Tamil , Telugu , Hindi , English & Kannada,.
Passport No G 9823612 .
Marital Status Married
Address No.76, Rajammal Street, Udhaya Nagar Extension, Behind Kaviya
Garden, Near Siva Subramanian Store, Porur, Chennai- 600 116.
Tamil nadu . India
Reference ; Mr. Raghavan (Senior Planning Engineer ) Harrihant Construction Company. Cell no—9380882208
.
Mr. Prakash ( M D ) Managing Director of Man gala Engg Company. Cell no—9791157550
Mr.Amoul Gerard. Project Leader , Jones Lang LaSalle,( Nokia Ph—3 ) Cell no-- 98413 28015.
-
July 27th, 2011, 06:08 PM
Post Count Number #3
ARTHUR IMMANUEL. S
arthur.immanuel AT gmail.com
OBJECTIVE :
A seasoned professional with excellent communication, organizational, and administrative skills seeking a challenging and responsible position in your concern where my experience can be utilized in support of company goals.
ACADEMIC QUALIFICATION :
- Bachelor of Production Engineering from Karunya Institute of Technology, in 2002.
- Certificate course in Piping Engineering along with PDMS from MIT-Pune.
- Approved QC-Engineer for OAG Underground Piping by TECHNIP, ADGAS.
- Certified HSS installation (Heat Shrinkable Sleeves Installation) Engineer from RAYCHEM.
- Offshore Safety course conducted by Adgas.
- CWI certification from AWS (Awaiting for result).
- ASNT-SNT-TC-1A Level II Certification in
- Ultrasonic Testing
- Magnetic Particle Testing
- Penetrant Testing
- Radiographic Testing
Professional Experience
Nine Years experience in the field of QA/QC , Welding , Inspection & Piping for the Construction, Erection, Installation, Fabrication and Inspection activities Flanges Parallelism of Pumps , Piping Erection , Test Pack Review , Hydro / Pneumatic test for Piping for Process , Structural Verticality and alignment checking , Fixed and Internal Floating Roof Storage Tank Welding monitoring , Leak Testing and welding activities and Onshore/Offshore Pipelines, Plant Piping, Jackets,Piles,Decks,Process Platforms, Off-shore Piping, Off-shore Structures, Fabrication Shop for Oil & Gas , Refinery ,Petrochemical Plant , Power Plant and other related Industries.
WORK EXPERIENCE
- ORGANISATION : VELOSI INSPECTION SERVICES (Nov 10 to Till date)
PROJECT-1
Designation : Inspection Engineer (THIRD PARTY INSPECTION)
Project : MHN PROCESS PLATFORM & LIVING QUARTERS
Client : LARSEN &TOUBRO-Contractor, ONGC-Client
.
PPROJECT DESCRIPTION : Onshore & Offshore Piping , Structures , Jackets , Piles , Decks , Platforms , Living Quarters Construction & Erection for M/S Oil n Natural Gas Corporation Limited(ONGC), India.
Working as a Client Authorized TPI Inspection Engineer for the above Project.
- ORGANISATION : TARGET CONSTRUCTION – ABUDHABI (UAE) (Sep 06 to Aug 10)
PROJECT-1
Designation : QA/QC Engineer (Piping – Offshore)
Project : OAG-1 (Offshore Associated Gases), DAS ISLAND
Client : Technip-Contractor, Adgas-Client
Period : May 2008 to Feb 2010d.
PPROJECT DESCRIPTION : Underground Piping works for the OAG1 for the ADGAS refinery expansion at DAS Island.
PROJECT-2
Designation : Quality Control Engineer
Project : SINCLAIR KNIGHT MERZ (CLERMONT COAL MINE)
Client : MAN TAKRAF
Period : Sep 2006 to Apr 2008td.
PROJECT DESCRIPTION : Manufacturing of tripper and spreader for mining applications for RioTinto Coal Mine.
- Organization :ZION INDUSTRIES LTD, (Fabrication of pressure vessels) Chennai
(Engineer-QC) - May 2002 – Sep 2006
PROJECT DESCRIPTION : Fabrication of pressure vessels and heat exchangers.
JOB RESPONSIBILITIES :
- Review of drawings, specifications, procedures, welding process, testing methods etc. & maintaining records for compliance with codes & project specifications.
- Sound knowledge of materials and their composition for construction.
- Conversant with international codes and standards like ASME, ANSI, ASTM, API etc.
- Working towards the perfect coordination of client and contractor in maintaining the highest quality standards at job.
- Qualification of welders through the welding processes like SMAW, SAW, GTAW and FCAW
- Generate RFI (Request For Inspection) for various stage inspections and hold points along with the reviewing of project ITPs.
- Monitoring the Welders & Welding activities as per approved WPS.
- Material & Consumable inspection such as Pipes, Plates, Structural Steels, Pipe Fittings of various Grades, Welding Electrodes, Filler Wires &Flux, Paints etc; & Reviewing the Mill certificate (MTC) with respect to type, size, qty identification, Witness of Mechanical test and Visual Inspection, Preparing MIR and Monitoring the proper storage as per requirement
- Taking care of the HSS installation of entire piping along with the supervision of blasting and coating.
- Witnessing of surface preparation of SA21/2, Painting, Coating thickness measurement of GI structures and pressure vessels internal and external paint coatings using Elcometer & Peel of Test of various Painting Systems.
- Performing regular inspection on humidity check and anchor pattern during coating inspection..
- Witnessing hydrotest and flushing of the lines along with the preparation of the test packages of the same.
- Ensure Inspection of Measuring & Test Equipment used in the Project including are calibrated & their status identified.
- Performing regular site visits along with the client to ensure the quality is maintained at all points.
- Ensure customer complaints related issues are investigated and necessary corrective and preventive actions are implemented.
- Performing the required action along with the contractor for the closure of the NCRs.
- Representing the client meetings on behalf of the company for technical clarifications and discussions.
- Inspection of Fabricated Parts during stages as per QAP
- To monitor the welding activities as per Project spec and Procedure.
- Shop supervision & Online inspection, Maintaining daily Inspection / Quality Record.
- Preparation of Quality Plans for work to be executed & inspection release reports
- Performed & coordinated inspection with Clients during various stages of fabrication.
- Carrying out dimension and visual inspection in accordance with drawings and specification
- Checking drawing before erection and finished product as per the schedule
- Performing field inspection for ongoing welding and finished weldments at site
- Looking after all types of destructive and Non Destructive testing
I hereby declare that all the above mentioned are true to my knowledge.
S. Arthur Immanuel