RESUME :
Name : VADIVEL.V
Email : vadivelugi AT yahoo.com

EXECUTIVE PROFILE :
- QA/QC Engineer- Electrical with 5 years of experience in handling end to end electrical and instrumentation activities in oil field construction both in India and abroad
- Proven track record in handling the entire aspect of the project, construction management, quality control & handing over
- Exceptional communication & interpersonal skills, blended with superior team management & leadership skills

CORE COMPETENCIES :
Key Result Areas :
- Provided active support to quality management team for overall quality controls & also implemented QCP & standards
- Carried out joint inspection activities along with the client representatives on site work based on RFI with the help of supporting documents
- Conceptualized & implemented modifications in operating procedures to optimize resource utilization & ensure smooth operations
- Involved in preparation of documents, project reports & project programme for time and resource management
- Was responsible for performing quality check & issuance of conformance / non conformance report to the contractors
- Interacted with the engineers and supervisors on a regular basis, towards on time completion of the projects
- Prepared project reports & project programme for time and resource management and submitted the same to the client

PROJECTS & RESPONSIBILITIES :
Nov 2008 till Date
Employer Black Cat Engineering & Construction W.L.L
Doha, Qatar
Project : EPIC of SMOKELESS FLARE and AUTOMATIC BLOWDOWN SYSTEM & BLAST PROOF CONTROL ROOM BUILDING. Contract No : GTC – 07/158/ED
Client : M/s. QATAR PETROLEUM
DUKHAN – QATAR
Value of Work
Executed : US$ 28,000,000.00 (Approx.)
Position : QA/QC Engineer- Electrical
Responsibilities :
- Preparation of Quality related documents as per client’s requirement such as Quality control plan, ITP, Method statement and related work instructions and liaison with the client for the approvals.
- Responsible for incoming materials Inspection with respect to approved Specification, Data sheets, Material Approval and quality plan.
- Responsible for maintaining IMTE in the project site, coordination with laboratory for witnessing the calibration of the instruments such as Welding Machines, Quivers, Electrode Holding Ovens, Pressure Gauges & Recorders Level Transmitters, Pressure Gauges & Recorders etc.,
- Monitoring the installation and testing of various panels, such as 415V Switchgear Panels, 3.3KV Breaker Panels & LV Switchboards and HVAC as per the approved procedures
- Monitoring the installation and testing of LV Transformers (145MVA), Diesel power generators as per the Quality plan.
- Carrying out inspection for electrical installation and testing of Motors, motor control centre panels and Earthing to confirm that all quality aspects as per QP standards are met. Inspection was being carried out as per approved ITP’s and Method of Statements.
- Inspection for the Installation and commissioning of UPS and Battery chargers (AC & DC) along with the Client as per approved Procedure.
- Inspection for installation of Instrument junction boxes, Motor operated valves pressure & temperature transmitters, gauges and F & G system.
- Inspection for laying and testing of Fibre Optic Cable and Telecommunication system
- Responsible for resolving quality related issues in site, as per the approved Procedures.
- Co-ordination with Client to provide solutions for deviations on the equipments and to ensure that all standard requirements are met.
- Issuance of NCR, preparation of look-ahead schedules and ensuring that all the schedules are met.
- Taking preventive and predictive actions for the non conformities observed in site.
- To understand the QP (Qatar Petroleum) procedures, specifications and Engineering Standards and to implement at the work site for achieving a Good Quality Work.

01-03-2007 to 01-10-2008
M/S. Al Hassan Engineering Company SAOG
Muscat, Oman
Project : Qarn Alam Power Station project
120 MW Power Plant having Frame GE
9E Gas turbine with auxiliaries
Client : Petroleum Development of Oman
Position : QA/QC Engineer – Electrical
Responsibilities :
- Preparation of Quality related documents as per client’s requirement such as Quality control plan, ITP, Method statement and related work instructions and liaison with the client for the approvals.
- Responsible for incoming materials Inspection with respect to approved quality plan.
- Responsible for maintaining IMTE in the project site, coordination with laboratory for arranging calibration of the instruments and responsible for calibrating in- house equipments such as Welding Machines, Quivers, Electrode Holding Ovens, Pressure Gauges & Recorders etc.,
- Monitoring the installation and testing of various panels, such as synchronizing panels, generator control panel etc., as per the approved procedures
- Monitoring the installation and testing of Circuit breakers, Current transformers, Capacitance voltage transformers, surge arrestors and Isolators as per the Quality plan.
- Verification and testing of Motors and preparation of testing reports.
- Inspection for the Installation and commissioning of UPS and Battery chargers (AC & DC) along with the Client as per approved Procedure.
- Responsible for resolving quality related issues in site, as per the approved Procedures.
- Taking preventive and predictive actions for the non conformities observed in site.
- Responsible for monitoring of electrical items storage as per the contract requirements.
- Responsible for preparation of punch list inline with ITP requirements and to close the same.
- Responsible for preparation of as built drawings.
- Preparation of test packs as per the client requirements.

- To understand the PDO procedures, specifications and EngineeringReference Documents (ERD’s) and to implement at the work site for achieving a Good Quality Work.

01-09-2005 to 10-01-2007
M/S. CODE ENGINEERS PVT LTD
Mumbai, India
Project : AWTF, Bhaba Atomic Research Centre, Trombay, Mumbai, India.
Client : Bhaba Atomic Research Centre
Position : QC Inspector - (Electrical)
Job Responsibilities :
- Monitoring the installation and testing of various panels, such as synchronizing panels, control panel etc., as per the approved procedures
- Responsible for maintaining IMTE in the project site, coordination with laboratory for arranging calibration of the instruments and responsible for calibrating in- house equipments such as Welding Machines, Electrode holding Ovens, Pressure Gauge etc.,
- Monitoring the HT & LT Power cable laying & testing jobs.
- Played a major role in shut down jobs, especially for coordination, safe working, installation, testing, report preparation and timely completion.

Computer Skills :
Windows XP/Vista, MS Office, C++, HTML.

Personal Details :
Marital Status : Married
Languages Known : English, Tamil, Hindi and Telugu
Nationality : Indian