V.VENKATESH
Summary :
QA/QC Welding /Piping Inspector, a competent professional with over 7 years of work experience in Welding, NDT, Piping and Inspection. Demonstrated skills in inspection activities. Ensuring compliance to quality standards and maintaining all related documents. Distinction of handling in various projects like Construction of Petrochemical monomer plant, Gas and Oil Separation Plant; handled Pressure Vessels & Cross Country Pipelines with clients like Adgas, Adma, Technip,Takreer,& BHEL, NTPC in UAE & India. Proficient in undertaking QC activities related to Fabrication/ Erection/ Welding of Piping, Pipelines, Pressure Vessels in accordance with ASME B31.3, B31.4, B31.8, ASME sec VIII and Project specification. Possessing sound knowledge of medium and heavy fabrications including piping, boilers, vessels, platforms, general structures and maintenance welding.
PERSONAL DATA :
Date of Birth : 17.08.1981.
Nationality : Indian.
EDUCATIONAL QUALIFICATION :
- Diploma in Mechanical Engineering.
Technical Qualification :
American Welding society :
- Certificate Welding Inspector – CWI
- AWS Certificate no : 09074391
American Society for Non-Destructive Testing (ASNT) :
- Ultrasonic Testing (UT) : LEVEL II
- Radiographic Testing (RT) : LEVEL II
- Magnetic Particle Testing (MT) : LEVEL II
- Liquid Penetrate Testing (PT) : LEVEL II
TRICHY REGIONAL ENGINEERING COLLEGE SCIENCE AND TECHNOLOGY ENTREPRENEURS PARK [TREC-STEP]
- CNC Programming Control
- CNC Operating System
Nature of Work :
- Handling Inspection of various Stages in Piping, Structural and Pressure vessels.
- Familiar with the construction Drg., General Arrangement Drg, Piping and Instrument Diagram and Isometric Drg.
- Reviewing of test procedure, welding procedure specification, PQR, WQT ,method and statement.
- Witness and procedure qualification testing and qualified welder in both the manual P automatic welding.
- Checking the According criteria as per codes and process and standard specification (ASME B 31.3,AWS D 1.1,API 1104).
- Preparation of NDT test plan and Inspection test and plan.
- Preparation of Request and Reports for the clients and Co-ordinate with the client representatives.
- Preparation of Inspection Report and Final Document for Dossier
- Preparing test packages as per component list and line class.
- Inspection of the Pre Heating, Interpass temp and Post weld Heat treatment.
- Check the Essential Parameter’s as per the WPS Requirements and Quality Procedure.
- Visual and Gauge Inspection in Fit-up before and after welding.
- To check the Proper Electrodes are used for the Respective Materials and the temp has been Maintained as per the Electrode Manual.
- Review and According of Minimum certificate for Materials and welding Consumables.
- Qualifying the welders as per the Project Requirement.
- Repair percentage Analysis and tool boxtalks. For welders to control Repair percentage.
- Verification that Dimension and alignment tolerance of the Piping Systems are as per Constructs Specification.
- Witness of the Hydro and Pneumatic test.
- The Review Mandatery of Qc Activity Steps for ITP .
- To check Radiographic Film of Classification, Radiographic sensitivity, type of IQI, Subject and Film Contrast type of Exposure.
Working Experience :
Company : M/S DESCON ENGINEERING ABU DHABI, UAE
Duration : OCTO 2008 to TILL DATE
Position : QA/QC WELDING & PIPING INSPECTOR
Job Responsibility :
- To conduct Procedure qualification test & welder performance qualification test as per WPS & ASME sec IX & prepare the report.
- Inspection of Fit up, Weld Visual for fabrication of Piping.
- Inspection of liquid penetrant testing and Magnetic Particle testing.
- Verify that correct materials are utilized for all works.
- Ensure that the welders are qualified to the WPS.
- Check and record welding parameters and verify compliance with approved WPS.
- Review of approved welding procedure, Qualification records
- Liaise with the company representative for the conduct of day-to-day quality related activities of the service contract
- repair percentage analysis and tool box talks for welders to control repair percentage.
Company : M/s NDT CORROSION CONTROL SERVICES ABU DHABI, UAE
Duration : MAY 2006 to MAY 2008
Job Responsibility :
- Ultrasonic testing /DPI &MPI at HP feed gas project.
- Material testing various plate to be inspection.
- Visual and UT examination on weld at Hydromontaza and NPCC
- All pipe welds have been inspected for their integrity using MT & RT & UT techniques.
- Conducted visual and UT examination on weld
- NDT reports preparation and documentation as per requirements for DPT& Hygro testing.
- Test pack preparation documentation as client’s requirement.
- Hydro testing evaluation& dye penetrant testing of weldments.
Company : M/s V N D THOUSE, THUVAKUDI, TRICHY-15.
Duration : November 2005 to April 2006.
Job Responsibility :
- Windmill tower 1.25mw Flange’s and CS& LS inspections.
- Top ring adaptor legs and various thickness four items.
- CS Butt WELD Quality RT/UT Test checked.
- To check surface preparation.
- Carried out panetrant testing on values servicing [main steam valve, air vent valve]
- Pressure gauge valve, safety valve & etc and duct welding S’duct, squareduct
- ‘Conducted visual and UT examination all welding area’s.
Company : M/s BHARATH HEAVY ELECTRICALS LTD, TRICHY-14.
Duration : October 2004 to October 2005.
Job Responsibility :
- To inspect plates, pipes & Nozzles & all Welds
- Manual processing, auto processing evaluation of films.
- To check MPI method to ceiling grider carrier plate and nozzles. >16mm plate edge preparation.
- To Inspect Box, Column, Beam Fittup.
- To check all weld visual Inspection to Butt Joint & Lab Joint
- To Inspect Pipe, tubes and Non-pressure to scan UT method.
- To submit material Receiving/Verification Report.
- All the assemblies shall be inspected as per drawing .
- Dimensional variations shall not exceed the limits
- The difference between diagonals
- To check a all Butt & lab joint welding visually checked
- To visually inspect the job through liquid penetrant testing & Magnetic particle testing
- The circular ducts and chimney shells with / without flanges
and ovality checked
- The deviations from flattens of contact face of the flange
- To check Twist of section the stiffener location of wall & all dimensions after trial assembly checked
- To check all ducts face out
- To remove spatter, slack, rust, fittings & oil or grease check
- To check surface preparation, painting and identification.
- C.S But Weld Quality RT / UT Test checked.
- To check individual dimension of jobs as per drawing
- To maintain record of welders & welding operators and verify
Company : M/s Venus Engineering Company, THIRUVERUMBER, TRICHY-14
Duration : JUNE 02 TO SEP 04
Position : Q/C SUPERVISOR
Job Responsibility :
- To inspect on, vendors for BHEL Manufacturing coil structural, ducts columns and grider ceiling to thermal station boiler.
- To Check and verify individual dimension of jobs as per drawing.
- Worked as quality control inspection in BHEL.
- Manufacturing water wall and stream cooled panels.
- Stage wise inspection of structural fabrication.
- Performed visual inspection piping.
- Visual inspection strainer & coils.
- LPI & MPI carried out boiler components.
- Daily report to the inspection.
- To check the Edge preparation.
- To check <32mm plate edge preparation side MPI & LPI test.
- Electrode Road, Flux and Welding Oven Main dance.
- Welding Documents checked.
- To inspect welding area and cutting edge 100% MPI & LPI checked.
Date :
Place :
May 12th, 2012, 11:16 PM
Post Count Number #2
which welding electrode to use for buttering in all weld testing?