June 24th, 2008, 11:51 AM
Post Count Number #1
Doha Petroleum Construction : DOPET : Qatar : Rotating Equipment
Doha Petroleum Construction Co., Ltd.
http://www.dopet.com
Company Profile
DOPET was established in 1981 to cater the Oilfield Maintenance activity in the State of Qatar.
Catering to the fields like Oil, Gas, Petrochemical and Utilities Industries, both Onshore and Offshore, DOPET has now grown into one of the largest Mechanical Construction Company in Qatar.
Powered by a dedicated team of Professionals, a strong Workforce and sophisticated Machineries & Equipment, DOPET has successfully carried out diverse assignments in areas like Fabrication and Installation of Piping and Structural, Fabrication of Pressure Vessels & Tanks, Electrical, Instrumentation, Valve Overhauling, etc.
The key to our growth is the dedicated teamwork and commitment to quality and to Client's satisfaction, which has enabled us to provide outstanding services to our valued Clients.
Our extensive workshops and fabrication facilities on the Salwa Industrial Area and at Ras Laffan, are used to support our site works.
DOPET's workshops and construction divisions are supported by a modern and fully equipped plant and maintenance facility to ensure equipment is maintained to the highest degree and always available for our as well as client's use.
Project Engineer (Rotating Equipment)
Experience:
4 - 9 Years
Location:
Qatar
Education:
UG - B.Tech/B.E. - Mechanical, Petroleum
PG - Other
Industry Type:
Oil and Gas/ Power/Infrastructure/Energy
Functional Area:
Site Engg., Project Management
Posted Date:
06 Sep
Job Description
1. Promote established policy and objectives throughout the department to increase awareness, motivation and involvement.
2. Ensure focus on customer requirements throughout the department
3. Ensure that appropriate processes are implemented to enable requirements of customers and other interested parties to be fulfilled and objectives to be achieved.
4. Ensure that an effective and efficient quality/HSE management system is established, implemented and maintained in the department to achieve these objectives.
5. Ensure the availability of necessary resources in the Project
6. Decide on actions regarding the quality/HSE policy and objectives
7. Decide actions taken for improvement of quality/HSE management system
8. Receipt of tender / enquiry's
9. Clarify with clients as appropriate
10. Attend Mid tender meetings/site visits
11. Obtain sub contractor prices
12. Prepare and submit tenders
13. On award of contract, source and arrange to procure material, organise work team, coordinate with clients, sub-contractors
14. Visit site and de-bottleneck, monitor progress
15. Supervise planning/progress reports
16. Preparation of invoices
17. Prepare and claim for additional work if any
18. Liaise with workshop stores and accounts
19. Look after general safety aspects
20. Perform any other task, to the best of the ability of the job holder that the management may from time to time request.
Desired Candidate Profile
Mechanical Engineering Graduate with three (3) years experience related to Engineering Projects preferably in Oil & Gas Environment.
Training or Experience and Skills:
Can communicate in both written and oral English.
Knowledge of standard technical project specification required by the client.
Familiar with tenders, cost estimation, contracts, material requirement for EPIC contracts.
Familiar with Cost/Project Control Methods.
Computer Literate
Executive Name:
Royce Arapan Orbeta...
Address:
Not Mentioned
Email Address:
engrjobs@dopet.com
Telephone:
Not Mentioned
Reference ID:
PE 001
Keywords: Project Engineer
-
July 23rd, 2011, 03:22 PM
Post Count Number #2
IJT addict
Name : Gurumoorthi
Email : guruumoorthi AT gmail.com
Designation / Skillset : BE-MECHANICAL ENGG 2011 PASSOUT
Respected Sir/Madam
I have graduated as Mechanical engineer 2011 pass out with First Class and during my studies have done projects on DESIGN AND FABRICATION OF AUTOMATIC SURFACE COATING MACHINE and DESIGN OF AUTOMATIC WINDSHIELD WIPER AND AUTOMATIC POWER WINDOW USING HYDRAULIC SYSTEM. Adding on to it completed certification ANSYS12, EDGECAM, UNIGRAPHICS (NX2).
On the process of studying engineering been to various manufacturing industries and understood the concept of product manufacturing and its various material handling techniques.
The projects and studies what I have done got much appreciation from our college and universities.
Kindly give me a chance to explain about my skills and knowledge face to face.
Looking forward to hear from you.
Thanks and Regards
Resume :
CAREER OBJECTIVE
Seeking a challenging work environment where my technical skills are guided for the growth of the organization.
KEY SKILLS
- Strong communication, Presentation and interpersonal skills with high motivation level.
- Open to quickly learn new concepts.
- Building strong relations.
PROJECT
MAIN PROJECT
- “DESIGN AND FABRICATION OF AUTOMATIC SURFACE COATING MACHINE”.
Our project is to develop and the fabrication of an automatic surface coating machine. The machine coats the surface from the scanned image. The accuracy of this device will reduce or eliminate the rework of objects that have been coated incorrectly, Using lean and Six Sigma methods.
- Using the Lean manufacturing system materials scrap is reduced and maximum utilised.
- By using six sigma errors are eliminated in our project so accuracy of the product is increased.
MINIPROJECT
- “DESIGN OF AUTOMATIC WINDSHIELD WIPER AND AUTOMATIC POWER WINDOW USING HYDRAULIC SYSTEM”.
In which for the windshield wiper we have made an ideal design for optical sensing system, and built up algorithms for wiping modes based on the quantification of detected rainfalls in order to meet an operator's expectation for wiping rain, Once the optical sensor detects rain drops the controls trigger the windshield wipers to activate. And an automatic opening and closing device for a window which has a extend and retract telescopic cylinder for opening and closing the window.
CERTIFICATIONS
- EDGECAM
- ANSYS12,
- Unigraphics-NX2
SOFTWARE PROFECIENCY
- Operating System : Windows 2000/XP/7
- Package : MS-Office
- Design Software : ANSYS12, Unigraphics-NX2, PRO-E
DWG Editor, Solid Works, EDGECAM.
TRAINING
- Undergone Inplant Training at DHARANI SUGARS, TIRUNELVELI from 7 th June, 2010 to 12th June, 2010.
Learned about the processing of sugar cane and extracting the various products from it, reuse techniques for minimal waste.
- Undergone In plant Training at UDHAYAKRISHNA ENGINEERING WORKS, Coimbatore from 1st june,2010 to 5th june,2010.
Learned about fabrication and manufacturing of submergible pumps which are used to lift water from boar wells to very high water heads.
AREAS OF INTEREST
- Product Designing
- Strength of Materials
- Production Engineering
EDUCATION QUALIFICATION
2007 - 2011 : B.E. in Mechanical Engineering at Dr.Mahalingam
College of Engineering &Technology, Pollachi with
CGPA 7.32
2006 - 2007 : HSC at Central Hr.Sec.School, pollachi; 66.25%
2004 - 2005 : SSLC at Government Hr.Sec.School, palladam; 57%
CO - CURRICULAR ACTIVITIES
- Participated in aero modeling competition held at DR.MCET, Pollachi.
- Workshop on line follower robotics at Loyola College, Chennai.
- Participated in Robotics workshop held at C.I.E.T, Coimbatore.
EXTRA-CURRICULAR ACTIVITIES
- Won first place in gaming counter strike at C.I.T, Coimbatore.
- Represented college BALL BATMITON team in TIES-2009
- Participated in AD-MAKER competition held at Sri Shakthi College of Engineering and Technology,Coimbatore.
I hereby declare that the information furnished above is true to the best of my knowledge and belief.
Place :
Date : V.GURUMOORTHI
-------------------------------------------------------
More Information about this submission and submitter :-
___________________________________________________
Submission ID : 4395572
Date & Time : 21st Jul 2011 7:28 AM (UTC)
IP Address : 115.184.171.2
Browser Info : Mozilla/5.0 (Windows NT 6.1; rv:6.0) Gecko/20100101 Firefox/6.0
Predicted Country : India
-
July 27th, 2011, 11:17 AM
Post Count Number #3
Application for the post of Rotating EquipmentEngineer
Resume A. SIMON RAJ
E mail – simonraj1973 AT yahoo.co.in and simonraj99 AT gmail.com
Languages Known : Tamil, English, Malayalam and Hindi
Objective
To work in a professional environment that will enable me to utilize my talents to the maximum extent and to be on par with latest technological developments.
Summery of Information
- 16 years experience on installation, commissioning and maintenance, experience in the field of oil, Water treatment, Kaolin and Glass plant .
- Experienced with computerized maintenance and material management system.
- Familiar with hazardous area classification and safe working practices.
Educational Qualifications
- Diploma in Mechanical Engineering.(Board Of Technical Education Tamil Nadu , India)
Training and Skills Acquired
- Heavy Vehicle Factory Avadi(Ministry Of Defense)
- Auto Cad Drawing
Present Works Experience :
Senior Engineer : ASHAPURA MINECHEM LTD,
Sy. No : 328/2, Kinfra Apparel Park,
Menamkulam, Trivandrum,
Kerala – 695586.
Kaolin Division
Main Accountabilities
Responsibilities of Planning and Execution of Following equipments Erection,
Commissioning, Running Maintenance and developmental works.
Rotating Equipments :
Rotary Kiln. Dia. 3.8m x Length 45 mtrs. Rotary Driers. Dia. 2.5m x Length 24. Mtrs. Rotary Coolers Dia 2.5 x 20m long, TGM 160 Super Pressure Trapezium Grinding Mills, Super Fine Air Classifiers, Single Toothed Roll Crushers, Agitators, Ribbon Blender, Air Blowers, Roots Blower, Air Compressors, Various types of Pumps, Rotary Air Lock Valves, etc…
Static Equipments
Gassifiers, Bag Filters, Storage Silos, Water and Chemical Storage Tanks, Filter Press model 1500/110, Cooling Towers, Central Ventilation System, Various types of Valves, Vibro Screen, De Gritter Units, De Laminator, Packing Machine, etc…
Conveying Systems
Pneumatic Conveying System, Screw Conveyers, Belt Conveyers, Bucket Elevators
Junior Engineer : Haden International Group Ind. Ltd.
C/o Saint Gobain Glass India Ltd, 1-A, Sipcot Industrial Park, Sriperumpudur, Kanchipuram Dist, from Aug 2005 to Aug 2007.
This facility is Glass Manufacturing Unit
Main Accountabilities
o Complete responsibilities of Utility Operation and Maintenance activities of Water Treatment Plant, RO Plant, Chiller (Trane), Air Compressor (Kaeser), Air Handling Unit 10000 class, Boiler and Fire Hydrant System
Gulf Experience Details.
Mechanical Foreman : M/S AL YAMAMA CO.
Dammam, KSA.
From Aug. 2001 to May 2005
Main Accountabilities
o Maintenance activities of on Desalination plant, Sewage treatment plant and HVAC systems.
o Executing of Pipeline fabrication erection and Commissioning works
o Prepare the piping Drawing in Auto cad.
o Participated major plant shut down activities.
o Involved installation, testing, commissioning and maintenance activities of various range of Centrifugal, reciprocating, screw, vacuum, submergible and deep well pumps.
o Maintenance activities of Reciprocation Air Compressor, Diesel Generator, Chillers and Air Handling units.
o Maintenance activities of Various type of Gate, Globe, Diaphragm, Butterfly, Ball, Non return and control Valves.
Works Experience
Supervisor : Gulf Engineers and Construction India Pvt. Ltd.
C/o Indian Additives Ltd.
Manali, Chennai – 68.
From April 1995 to July 2001..
This facility is Lubrication oil Additives Plant
Main Accountabilities
o Maintenance activities of Piping, tanks, Reactors, Hot oil units, Cooling tower, Pumps, Compressors and all Mechanical installations.
o Raise work permits and take a lead role.
o Participated major plant shutdown activities.
o Involved Installation, testing and commissioning activities for new pipeline projects.
Nature of Duties
o Planning and Executing in Complete Kaolin Plant Project Erection works.
o Preparing the materials list as per Drawing and Space in plant.
o Preparing the works Scheduled and man power requirement.
o Responsible to Equipment Installation, Inspection and Commissioning.
o Timely absorption of new initiatives (like Project, Modification, etc…)
o Updated all the drawings and technical specification of the equipment into system.
o Re use and recycle equipment wherever possible.
o Investigating failure in maintenance and taking corrective action.
o Trouble shouting with an objective of finding Permanent solution.
o Ensure the good upkeep of the department.
o Preparing spare parts list for each equipments.
o Meet SHE target for there area.
o Participated major plant shutdown activities.
I hereby declared the above information furnished by me is correct and true to the best of my knowledge.
A. Simon Raj
-
December 30th, 2012, 08:18 PM
Post Count Number #4
Post applied : Senior .Q C inspector (Welding / Piping)
KANAI DEBNATH.
Email id = kanai_mainak AT yahoo.co.in or kanaidebnath04 AT gmail.com
OBJECTIVE :
A CHALLENGING CAREER AS A QUALITY CONTROL & EXPEDITING PERSON IN THE FILED OF MECHANICAL CONSTRUCTION.
PERSONAL STRENGTH. :
To peruse a challenging opportunity and a position in CCC co. and S K Eng co. MCSC co. AGIP co. well reputed organization that offer good opportunities and challenging work environment in return world help in building my knowledge, experience and academic capabilities. My experience proves to be my strength. Confidence, ability to work hard, learns more strive for achievement and my never set die attitude with positive outlooks.
SYNOPSIS :
Over 10 years of experience in inspection, testing and QA / QC activities in the oil & gas field
Familiar with international standard like ASME section II, V, VIII, IX, B31.3, B31 knowledge
In welding of various materials like Carbon Steel, Stainless Steel, Copper Nicole, Presser vessel And Exchanger.
TECHNICAL QUALIFICATION :
Diploma in Mechanical Engineering from International Council for management studies (Chennai)
NON – DESTRUCTIVE TESTING QUALIFICATION
Certified As ASNT Level II – in
Ultrasonic Testing Method (UT)
Magnetic Particle Testing Method (MPI)
Penetrate Testing Method (PT)
Radiography Testing Method (RT)
Last experience 14th months.
From : January 29th 2011 to 8th march 2012.
WITH CCIC (CONSOLIDATED CONTRACTORS COMPANY)
Clint : Agip kco. (Agip Kazakhstan North Caspian Operating Company N.V.
Project : Kasagan Development experimental project (offshore). D- ISLAND, A-ISLAND.
AREA OF EXPOSURE :
Review of Plot, key plan, root, P&ID & isometric drawing
Weld visual inspection.
Review the pre heating, post heating, PWHT procedure.
Preparation of WPS.
Witness of Hydro and Pneumatic test.
Witness of PWHT.
Prepare daily fit-up and welding inspection reports.
Fit-up inspection and visual inspection for high pressure piping & critical piping.
Material receiving inspection as per drawing & specification.
Verification & review & approval of quality assurance plan & inspection test plan.
Witness of NDT.
Witness of positive material identification & hardness testing.
Material identification with respect to test certificates & fill up inspection as per given design.
Drawing & joint design.
Qualifying welders as per ASME section IX.
Familiar about different welding methods (SMAW, GTAW, FCAW, SAW).
Familiar about S.S, Alloy steel, C.S, LTCS, & M.S, based materials & electrodes.
Prepare & review of test pack & inspection of the piping loops as per isometric,
Check list & issuing punch list.
Monitoring the job according to quality work procedure quality system procedure, quality control procedure & applied international standards & codes.
Running PQR & controlling of PWHT work.
Implementation of QA / QC procedure as per ISO norms & standards.
Organization : Consolidated Contracting International Company.
Position : Welding Inspector. From: 01 December 2008 to 31 Aug 2010
Clint : Agip kco. (Agip Kazakhstan North Caspian Operating Company N.V.
Project : Kasagan Development experimental project (Onshore).
AREA OF EXPOSURE :
Review of Plot, key plan, root, P&ID & isometric drawing
Weld visual inspection.
Review the pre heating, post heating, PWHT procedure.
Preparation of WPS.
Witness of Hydro and Pneumatic test.
Witness of PWHT.
Prepare daily fit-up and welding inspection reports.
Fit-up inspection and visual inspection for high pressure piping & critical piping.
Materials receiving inspection as per drawing & specification.
Verification & review & approval of quality assurance plan & inspection test plan.
Witness of NDT.
Witness of positive material identification & hardness testing.
Material identification with respect to test certificates & fill up inspection as per given design.
Drawing & joint design.
Qualifying welders as per ASME section IX.
Familiar about different welding methods (SMAW, GTAW, FCAW, SAW).
Familiar about S.S, Alloy steel, C.S, LTCS, & M.S, based materials & electrodes.
Prepare & review of test pack & inspection of the piping loops as per isometric,
Check list & issuing punch list.
Monitoring the job according to quality work procedure quality system procedure, quality control procedure & applied international standards & codes.
Running PQR & controlling of PWHT work.
Implementation of QA / QC procedure as per ISO norms & standards.
Organization : Consolidated Contracting International Company.
Position : Welding Inspector. From: 27th January 2007 to 10th September 2008.
Clint : FLOOR DANIEL MAIN CLINT AND OTHER CLINT TECHNEP (Italy)
Project : OL2K ETHYLENE PROJECT (Onshore).
AREA OF EXPOSURE :
Review of Plot, key plan, root, P&ID & isometric drawing
Weld visual inspection.
Review the pre heating, post heating, PWHT procedure.
Preparation of WPS.
Witness of Hydro and Pneumatic test.
Witness of PWHT.
Prepare daily fit-up and welding inspection reports.
Fit-up inspection and visual inspection for high pressure piping & critical piping.
Material receiving inspection as per drawing & specification.
Verification & review & approval of quality assurance plan & inspection test plan.
Witness of NDT.
Witness of positive material identification & hardness testing.
Material identification with respect to test certificates & fill up inspection as per given design.
Drawing & joint design.
Qualifying welders as per ASME section IX.
Familiar about different welding methods (SMAW, GTAW, FCAW, SAW).
Familiar about S.S, Alloy steel, C.S, LTCS, & M.S, based materials & electrodes.
Prepare & review of test pack & inspection of the piping loops as per isometric,
Check list & issuing punch list.
Monitoring the job according to quality work procedure quality system procedure, quality control procedure & applied international standards & codes.
Running PQR & controlling of PWHT work.
Implementation of QA / QC procedure as per ISO norms & standards.
Organization : S K Engineering & Construction Co, Ltd.
Position : Piping Inspector. From: march 1998 to 31 may 1999.
Clint : KNPC, Mina Al-Ahmadi Refinery.
Project : AGR Project. (Kuwait)
Extensive Knowledge of piping (Seamless & ERW) and very well versed in standards as shown below.
SAES : API. ASTM. ASME. and ISO 9001 ((QMS).
Site experience in Oil & Gas Project in Kuwait. KNPC.
Adaptability and endurance to work anywhere with available resources.
Versed in working with the latest industry solution based software’s.
Responsibilities :
Verification of isometric drawing with respect to P&ID.
Reviewing the approved quality plans, manuals and scope of work to perform the required inspection.
Witnessing the Hydro testing of the pipe lines, drums and vessels..
Prepare hydro test packages, line check and punch listing.
Control of non conformities issuance of punch list.
Coordinating with client/consultants while the inspection is being carried out and offer any clarification is required.
Witnessing of pneumatic test, hydro-test, and flushing; system lay-up both in and in erection field.
Preparing and maintaining various QA/QC documents and final test packages.
Witness of alignment, orientation and dimensions of installed piping.
Assures that all joints are exposed for examination during pressure test.
Ensuring vents are open when filling and draining lines.
Conform repairs, re-testing and re-inspection in accordance with specifications.
Making a re-instatement punch list and clearing the items.
Witnessing of Flange joint assembly and bolt torque.
Ensure the blinds are removed and correct rating gaskets are installed.
Inspection of gaskets, supports, valves prior to line reinstatement acceptance as per the latest drawing for construction, codes and specification standards.
Prepared documents, procedures for inspection method ,inspection and testing plan in
Organization: MC SC Co. (Bahrain)
Position: Piping Inspector. From: January 2000 to march 2006.
Clint: BAPCO refinery, IGPL,
Project: Various project in Bahrain. Like a Sculpture project, Refinery Extension face II,
Responsibilities :
Verification of isometric drawing with respect to P&ID.
Reviewing the approved quality plans, manuals and scope of work to perform the required inspection.
Witnessing the Hydro testing of the pipe lines, drums and vessels..
Prepare hydro test packages, line check and punch listing.
Control of non conformities issuance of punch list.
Coordinating with client/consultants while the inspection is being carried out and offer any clarification is required.
Witnessing of pneumatic test, hydro-test, and flushing; system lay-up both in and in erection field.
Preparing and maintaining various QA/QC documents and final test packages.
Witness of alignment, orientation and dimensions of installed piping.
Assures that all joints are exposed for examination during pressure test.
Ensuring vents are open when filling and draining lines.
Conform repairs, re-testing and re-inspection in accordance with specifications.
Making a re-instatement punch list and clearing the items.
Witnessing of Flange joint assembly and bolt torque.
Ensure the blinds are removed and correct rating gaskets are installed.
Inspection of gaskets, supports, valves prior to line reinstatement acceptance as per the latest drawing for construction, codes and specification standards.
Prepared documents, procedures for inspection method ,inspection and testing plan in
Computerized environment.
I hereby declare that all the information mentioned above is true to the best of my knowledge and belief
You’re faithfully
Kanai debnath