www.perfexgroup.com Perfex Technocrats Pvt Ltd Visakhapatnam : Instrumentation Electrical Site Engineer

+ Ask Question / Post resume
Results 1 to 6 of 6
  1. Post Count Number #1
    Super Moderator
    Join Date
    April 18th, 2008
    Location
    Tuticorin
    Posts
    7,026

    www.perfexgroup.com Perfex Technocrats Pvt Ltd Visakhapatnam : Instrumentation Electrical Site Engineer

    Perfex Technocrats Pvt Ltd Visakhapatnam, : Site Engineer – Instrumentation / Electrical
    Website: http://www.perfexgroup.com
    perfexgroup.com

    Designation: Site Engineer – Instrumentation / Electrical
    Experience: 3 - 8 Years
    Location: Visakhapatnam
    Industry Type: Semiconductors/ Electronics
    Functional Area: Site Engg., Project Management

    Job Description:
    The Candidate should have experience in industrial Electrical or Instrumentation projects like, supervising in installation, testing & commissioning of electrical / instrumentation equipments according to the drawing given by the client, coordinating with client & head office, preparing as built drawings, preparing work progress reports, estimating the work and planning for manpower, preparing schedules for the work etc.,

    Desired Candidate Profile:
    BE/Dip. in EEE/ECE/ Instrumentation with Min 3-10 year exp. Knowledge of Engineering, Cost Planning, Installation, Function & logic check procedures, Commissioning of DCS, PLC etc.,
    People who got the relevant experience and willing to work anywhere in India only can apply.

    Head Ofiice-Visakhapatnam But posting will be Anywhere in India ( wherever our projects are going on) at present projects at Orissa & Chattisgarh

    Company Profile:
    Perfex Technocrats Pvt. Ltd, which can boast of having a Well-trained & Qualified Team using latest technological advancement, with innovative ideas and having 80% business share contributed by same clientele, reflect the Customer delight.
    We Provide Electrical & Instrumentation Services to Industries Like :
    Steel Plats, Pellet & Benefication Plants,Power, Automobile, Paper, Sugar, Textile, Pharmaceutical, Food, Petrochemical, Hotel, Cement, Distilleries, Buildings Chemical & Fertilizers,Bio Fuel,Process etc.

    Address:
    Perfex Technocrats Pvt Ltd
    1st Floor, Perfex House
    45-44A9/3
    Akkayyapalem
    Visakhapatnam,Andhrapradesh,INDIA 530016

    Email Address: perfex2006@yahoo.co.in

    Keywords: Site Engineer- Instrumentation, Electrical, BE in Instrumentation, Visakhapatnam
    Last edited by muthukalee; October 19th, 2011 at 10:49 AM.

  2. Post Count Number #2
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    seeking job at your organization

    Sir ,
    Sub :-Seeking job at your organization

    This is chaitanya .I had poses my btech mechanical and also having the working experience as site engineer (1 year) in OCL ltd (cements). I am also doing the NDT level2 course .
    Thanking you sir,
    E Krishna chaitanya.

  3. Post Count Number #3
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    B-TECH IN APPLIED ELECTRONICS&INSTRUMENTATION(FRESHER)

    BIODATA

    SHARIKA.K.T
    E-mail : sarikabalagopal AT gmail.com

    CAREER OBJECTIVE
    Seeking an opportunity to utilize my skills and abilities in an organization that offers professional growth while being creative, innovative and flexible. Perform effectively my assigned responsibilities and contribute to the growth of organization.
    MY STRENGTH
    Total devotion to my work with patience and enthusiasm. Ability to assimilate and convert it into practical .Devote my complete knowledge for my job and do my level best for best results.

    ACADEMIC QUALIFICATIONS :
    Examination Discipline School/College Board/University Year Of Passing Percentage
    B Tech Applied electronics&
    instrumentation Vimal jyothi engineering college,
    Chemperi,Kannur Kannur university
    2011
    63.29
    (Up to 6th semester)
    12 th Science
    (Mathematics+ Biology)
    Stream Jawahar navodaya vidyalaya Kannur CBSE
    2007
    71.2
    10 th

    Jawahar navodaya vidyalaya Kannur CBSE
    2005
    76
    ACADEMIC PROJECT :
    - Mini Project : Intellegent Vehicle Pannel System
    - Main project : Chemical Preparation &Dosing
    - Seminar : Nonlinear Interferometric Vibrational Imaging of molecular species
    SOFTWARE PROFICIENCY :
    - Languages : C,
    - Programming in C,PLC,DCS
    - Operating System : Windows XP,Assembly Language Programming in 8086
    TRAINING ATTENDED :
    - Completed the course in DCS&PLC OVERVIEW conducted by the training center of Yokogawa India Ltd.
    ACHIEVEMENTS :
    Won many prizes in school level extra curricular activities
    LANGUAGE SKILL :
    Oral & Written skill in English, Malayalam,Hindi

  4. Post Count Number #4
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    Elect./inst. Site superintendent

    Career Profile

    Over eighteen (18) years of experience as Elect. & Inst. Superintendent in various Industrial Sectors. Working for Saudi Arabia for more than 14 years. My Overseas employment is of Elect & Inst. Superintendent position with Saudi Chevron(S-chem),Saudi Kayan,Saudi International petrochemical Company(Sipchem) Jubail, Linde engineering in Sabic National Industrial Gases Co in Yanbu Phase III, Al-Jomaih & Petrobau Saudi Arabia Co. Ltd ( APSA) & S.A. Kent Co. Ltd. for Polymer Grade Propylene Plant in Yanbu, Senior E & I Supervisor with Technicas Reunidas Gulf S.A. & S.A. Kent Co. Ltd. for Diesel Hydro Treater Unit in Yanbu Aramco Refinery, Flour Arabia Ltd. in Yanpet Polypropylene project in Yanbu, Saudi Toyo Engg. In Jubail Petrokemya Polyethylene Project, ABB-Elsag Bailey Hartmann & Braun & S.A. Kent Co. Ltd. for the Royal Commission Project and Aramco Refinery upgrade project in Rastanura. A result-oriented person, high performer flexible, interpersonal communication skills. Accomplished assigned jobs on professional and organized manners with high-level management. Always been proactive I terms of fulfilling my responsible and have worked diligently to meet company objectives at all times.

  5. Post Count Number #5
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    MOHAMMAD KHALID IQBAL
    E-Mail :- Khalid.engr AT yahoo.com/x.ray.qatar AT gmail.com
    ________________________________________ In quest of managerial assignments as Project Management / Project Coordination domain with an organisation of high repute preferably in India, QATAR.
    Prιcis
    - B.E. professional with nearly 5 years of experience in Strategic Planning of Projects, Coordination and Project Management of ELECTRICAL.
    - Last associated with QATAR POWER CONSTRUCTION AS PROJECT ENGINEER.
    - Gained exposure in design, development and manufacturing of ELECTRICAL AND CIVIL.
    - Administering electrical and civil related (as per site required) projects and ensuring its timely completion & with high class work quality as per given words on contracts.
    - Proficient at providing end-to-end coordination, development of products from requirement analysis to system study, designing, documentation and implementation.
    - Adept at conducting Communication Design and Development including Layout, Analysis, Evaluation Prototype Build-Up and Testing of Electronic & Communication Components.
    - Exceptional communication, collaboration & team building skills with proficiency at grasping new technical concepts quickly and utilize the same in a productive manner.
    - Demonstrated abilities in comprehending new technologies with ease.
    Skills Set
    Managerial
    Project Management
    - Analysing the project requirements such as Client / user interaction for requirement gathering, risk assessment, finalization of technical specifications and discussions for effort / cost / time estimation / issue and client co-ordination and reporting.
    - Evaluating and assessing requirement of system software for selecting appropriate technologies.
    - Delivering and implementing the project as per scheduled milestones.
    Team Management
    - Training clients and customers on the product and extending them onsite support including deployment and maintenance of software product.
    - Delegating the work to the team members on a priority basis and also basing on the skill set.
    - Monitoring the performance of the team members and ensuring accomplishments of targets.
    Technical
    Operating System : Windows 98, 2000, XP.
    Languages : VB, Oracle 9i.
    Office Suite : Ms Word, Excel.
    Project Tool : Microsoft.net,
    Career Recital

    April2’2011– Till Date
    QATAR POWER CONSTRUCTION, as Project engineer
    - Preparation of site activity planning in the detailed project schedule.
    - To review the approved drawings, planned activities and confirm the actual resources including the supervisors, workers, equipment, documentation, work method and sub contractors as applicable during the site planning stage.
    - Daily and long term planning at site, coordination, control and efficient utilization of the required resources for all site activities.
    - Supervise the foreman to ensure assign work to be completed according to the approved drawings.
    - Coordination with QA/QC Engineer in receiving and inspection materials at site.
    - Reconciliation of all mark up drawing needed for As-Built Drawings.
    - Maintaining proper handling and storage of materials, tools, equipments etc at site.
    . Assuring safety measure require for the project.
    - Over all coordination with QA/QC Engineer, Project Engineer, other Engineers at site and sub-contractors for materials, equipments etc.
    - Coordination with SEC representative on inspection/test witness and any other contractual obligation.
    - Coordination with Testing & Commissioning Team and SEC witnessing Team to precede Testing & Commissioning as per planned schedule.
    - Monitoring and control of the relevant company procedure to ensure that they are followed correctly. Rectify and implement any deficiencies reported through non conformance reports.
    - Water supply system & motor control systems.
    - Erection of Control & Protection System, SCADA & Telecom System.
    - Installation of internal & external lighting and lightning system.
    - Cable laying HV, MV & LV.
    - Clearing the Punch/Snag List with SEC after the work completion.
    March12’2007 – april1’2009
    Unicon infradev engineering private ltd as Engineer / project engineer
    - Over all coordination with QA/QC Engineer, Project Engineer, other Engineers at site and sub-contractors for materials, equipments etc.
    - Coordination with SEC representative on inspection/test witness and any other contractual obligation.
    - Coordination with Testing & Commissioning Team and SEC witnessing Team to precede Testing & Commissioning as per planned schedule.
    - Monitoring and control of the relevant company procedure to ensure that they are followed correctly. Rectify and implement any deficiencies reported through non conformance reports.
    - water supply system & motor control systems.
    - Erection of Control & Protection System, SCADA & Telecom System.
    - Installation of internal & external lighting and lightning system.
    - Cable laying HV, MV & LV.

    July’2006 –march’2007
    Shah industries private ltd,patna Bihar
    - Over all coordination with QA/QC Engineer, Project Engineer, other Engineers at site and sub-contractors for materials, equipments etc.
    - Coordination with Testing & Commissioning Team and SEC witnessing Team to precede Testing & Commissioning as per planned schedule.
    - Cable laying HV, MV & LV.
    - Preparation of site activity planning in the detailed project schedule.
    - To review the approved drawings, planned activities and confirm the actual resources including the supervisors, workers, equipment, documentation, work method and sub contractors as applicable during the site planning stage.
    Significant Highlights
    - Successfully handled key project on GTC 226/GTC 198/GTC196.
    - Managed key client such as Kaharma.
    Key Projects Handled
    Project#1
    Title : GTC 226/2008 for Qatar power construction WLL.
    Client : KAHARMA QATAR.
    Team Size : 20 Members.
    work :maintenance and upgrading of substation.
    Project Description
    Upgrading the rating of RING MAIN UNIT, FEEDER PILLERS, TRANSFORMER,LIKE before feeder pillar coming 800 or 1250 Ampere but recently 2500 ampere, transformer 500 or 800 or 1000 or 1250 KVA but recently 1600KVA According to the requirement of client .
    ________________________________________
    Project#2
    Title : GTC 196/2008 for Qatar power construction WLL.
    Client : KAHARMA QATAR.
    Team Size : 20 Members.
    work : construction of substation ,
    Project Description
    Construction based on project GTC196/2008 area newly establishing like bin omran,thumama,al khor,industrial area .
    ________________________________________
    Project#3
    Title : GTC 198/2008 for Qatar power construction WLL.
    Client : KAHARMA QATAR.
    Team Size : 20 Members.
    work : direct supply service .
    Project Description
    Direct service from main LV cable to home by using service cable base on distribution according to need. Generally we are using cable sizes of this like 4c 16, 35, 70,120,185,300 till.
    ________________________________________
    Project#4
    Title : GTC 212/2008 for Qatar power construction WLL.
    Client : KAHARMA QATAR.
    Team Size : 20 Members.
    work : diversion of HV cable mainly .
    Project Description
    This project is based on diversion or newly reqiurment or cable passing through private area.
    Project#5
    Title : DANWAY project in umm salal Qatar.
    Client : self work.
    Team Size : 20 Members.
    Work :work related to 3.3kv hv cable termination to give supply there generators.
    Project#6
    Title : sidra hospital & Research College in Qatar.
    Client : self work (main contractor is kentz).
    Team Size : 20 Members.
    work :work related HV termination 3c240 mm in block wise .

    ________________________________________
    Training / Seminar Attended
    - PMP Training program.
    - Seminars related to Business Development in terms of BMS / Project Planning & Managements.
    Scholastics
    2006 B.E. (Electronics & Telecommunication) from MAULLANA AZAD COLLEGE OF ENGINEERING &
    TECHNOLOGY.Patna (Magadh University).

  6. Post Count Number #6
    Guest Poster
    Join Date
    August 14th, 2008
    Location
    Your Heart, Delhi
    Posts
    76,213

    SOUJANYA MYLA
    E-mail :soujanyamyla AT yahoo.com
    :soujimyla AT rediffmail.com
    Summary
    - Having 1 year 6 months of work experience in R&D field.
    - Having 2 years of work experience in Chemical Leaching Plant.
    - Having 1 year experience as Graduate Apprentice Trainee.
    - Excellent communication and interpersonal skills.
    - Experience in gathering the project requirements and implementing them in the field as and when needed.
    - Good analytical ability, quick grasping power, and zeal for learning new things.
    Work Experience
    - Worked as a Sr. Electronics Engineer in Ardee Hi-Tech Pvt Ltd., Visakhapatnam from February 2011 to May 2011.
    - Worked as an Instrumentation Engineer in Chemical Leaching of Coal Pilot Plant (TATA STEEL) from March 2009 to January 2011.
    - Worked as an Electronics Engineer in Ardee Hi Tech Pvt Ltd., Visakhapatnam from January 2008 to February 2009.
    - Undergone training as a Graduate Apprentice Trainee in Visakhapatnam Port Trust from December 2006 to December 2007.
    Skill Set
    Core Technologies PLC and SCADA Programming Language of Allen Bradley (Rockwell).
    Core Technologies Maintenance, installation, commissioning of different types of field instruments and pneumatic valves.
    PCB Designing Using PCB123 schematic.
    Educational Qualification

    - Bachelors Degree in Electronics Engineering with an aggregate of 68.37% from J.N.T. University, Hyderabad in 2006.
    Professional Experience - Full Time Employee :
    Project No # 1
    R&D (Designing of SCA and CRM cards) Feb2011 – May2011.
    Client : Pilot Plant, in Korba.
    Organization : Ardee Hi Tech Pvt. Ltd
    SCA and CRM are Single Channel Analyser and Count Rate Metering cards used in coal plant for analyzing the ash content in a selected coal and the most commonly used type of sources in this testing process were Ce, Am, Co.
    Environment : PCB schematic and awareness of source and their hazardous effect.
    Responsibilities :
    - Involved in designing of the cards.
    - Involved in testing of the cards by using different types of coal with known ash content within them.
    - Involved in discussions on project requirements.
    - Involved in guiding others while handling the sources and working with them.
    Project No # 2
    Chemical Leaching of Coal Pilot Plant. Mar2009 – Jan2011.
    Client : TATA STEEL.
    Organization : Ardee Hi Tech Pvt. Ltd
    Leaching plant deals with the reduction of ash percentage from different types of coal samples collected. So this process involves different types of field instruments and different types of pneumatic valves and their installation, commissioning and maintenance. Interfacing these instruments and valves to the PLC and Automation of these using Rockwell make.
    Environment : PLC and SCADA programming of Allen Bradely Rockwell and Hart calibraters for instruments calibration. Hardware techniques for the pneumatic valves maintenance, troubleshooting.
    Responsibilities :
    - Worked on Automation part, interfacing of the different types of field instruments to PLC.
    - Worked on installation, commissioning and maintenance of the field instruments.
    - And even calibration part to some extent.
    - Worked on installation guidelines and maintenance of the pneumatic valves and even troubleshooting.
    - Involved in guiding the sub ordinates while performing the maintenance and troubleshooting works when it comes to the case of these field instruments and valves.
    - Even involved in guiding the sub ordinates in interfacing these field instruments and valves to PLC and in linking up of these interfaced to PLC tags as well to SCADA.
    - Even involved in generating the day to day reports of the health conditions of these instruments and the PLC panels functioning.
    - Involved in guiding the sub ordinates the safety precautions while doing the troubleshooting works.
    - Even involved in guiding the sub ordinates regarding their own safety measures while entering the field and while going in contact with any of the field related instruments, areas, panels etc.
    Project No # 3
    R&D (Radiometric Detection and Removal of Stones/Shale
    and Rice sorting machine and Digidose.) Jan2008 – Feb2009.
    Client : Coal Plant, in Gujarat.
    Organization : Ardee Hi Tech Pvt. Ltd
    Radiometric Detection and Removal of Stones/Shale deals with the Para card for detecting stones from coal over its way on the conveyor belt where we use the radiation sources for detecting the stone as density and dimensions of stone varies when compared with that of coal and even the intensity of the radiations emitted from the source decreases when the stone or any obstacle comes in the path of emerging radiations while compared with that of radiation passing through coal. And when stone is detected it is oozed out with high air pressure and coal free from stone on other side.
    Digidose is Digital Pocket Dosemeter which is used to calibrate the rate of human exposure to gamma radiations while dealing with dangerous sources in the laboratory, medical fields, R&D fields.
    Rice Sorting Machine used for separating colored rice grains from normal colored grains using 555 Timer. It is designed for 10 channels.
    Environment : Radiation sources, timers and amplifier cards.
    Responsibilities :
    - Involved in designing the rice sorting machine.
    - Digidose calculations and updating day to day data.
    - Designing of Para cards and testing them in the laboratory.
    - Generating awareness among the sub ordinates on the hazardous effects of the radiating sources when exposed to them without any preventive measures taken.
    - Calabrating the Digidose.
    - Testing and observation of the designed Para cards and Rice Sorting Machine.
    Project No # 4
    Trainee Dec2006 – Dec2007
    Organisation :Visakhapatnam Port Trust.
    Training undergone in fields like load cells which measure the quantity of coal passing on the belt and analyzing the depth of the sea using RADAR or Ultra sound and GP which is used for identification of the large ships entering the premises.
    Environment[]: Trainee.